May 1-6 | 6 | Traub, Millan-Gabet, Monnier, Berger, Pedretti, Carleton, Schloerb, Brewer, Lacasse | 3-beam comb. & PICNIC | Phase-closure |
May 7-20 | 14 | Berio, Stee, Bittar, Perrin, Foresto | FLUOR/NICMOS3 | Be and B[e] stars |
shared time | . | Perrin, Mennesson, Foresto, Ridgway, Merand | FLUOR/NICMOS3 | Mira stars |
shared time | . | Gerbaldi, Foresto, Perrin, Borde, Faraggiana, Lai, Delmas | FLUOR/NICMOS3 | Lambda Boo stars |
May 21-25 | 5 | Przygodda, Leinert, Schuller, Porro | FLUOR/NICMOS3 | MIDI calibrators & red giants |
May 26-June 2 | 8 | Monnier, Berger, IOTA CfA team | Vis. SM fiber & APDs | Cepheids |
June 3-11 | 9
-1/2 |
Weigelt, Beckmann, Dress, Hofmann, Malanushenko, Nussbaum, Ohnaka, Schertl, Traub, Millan-Gabet, Berger | MPIfR JHK beam-combiner camera | JHK Spectro-Interferometry |
June 12-July 2 | . | . | . | . |
shared time | 14
-1/2 -1/2 -1/2 |
Berger, Haguenauer, Kern, Malbet, Perraut, Millan-Gabet, Traub | Integrated Optics & PICNIC | Phase-closure meas. w/ IO |
shared time | 7
-1/2 |
Traub, Millan-Gabet, Monnier, Berger, Pedretti, Carleton, Schloerb, Brewer, Lacasse | 3-beam comb. & PICNIC | Phase-closure meas. with 3-beam combiner |
June 7
June 13 June 19 June 25 July 1 |
1/2
1/2 1/2 1/2 1/2 |
Ratner, Millan-Gabet, Traub | FLUOR/PICNIC | IM Peg GP-B, as can be accomplished by observers already on site with available equipment |
July 2-Aug 31 | 61 | Lacasse, Ahearn | Engineering | Rainy season |